20. CONSTRUCTION OF FACILITIES

 

(a) Arrangement for Construction of Receipt and Delivery Facilities. Subject to

conditions specified in this Section 20, Operator will construct or provide facilities

necessary for the receipt and delivery of Natural Gas or LNG into its system if

Operator determines (i) that no undue burden will thereby be placed upon Operator, and

(ii) that no impairment of Operator's ability to render adequate service to its

customers will result therefrom; and provided that Operator first is able to obtain

all necessary governmental and other authorizations.

 

(b) Method of Payment. In the event Operator constructs facilities at the request of

Buyer, Buyer shall pay Operator for the costs of such facilities in a manner agreed to

in writing by Buyer and Operator in advance of construction of any such facilities.

Such methods of payment may include, but shall not be limited to, a lump sum payment

covering all the costs of such facilities, including income tax gross-up and

applicable operation and maintenance.

 

(c) Construction of Other Facilities. Operator in its sole discretion may construct other

facilities in accordance with the regulations of the Commission.