GENERAL TERMS AND CONDITIONS

Construction of Delivery Tap Facilities

 

37. Construction of Delivery Tap Facilities.

 

37.1 For the purposes of this Section 37, "Requested

Facilities" shall mean Taps, M&R Equipment and

Laterals. Requested Facilities shall not include

major expansion of transmission facilities. "Tap"

shall mean a delivery tap and shall include, but

shall not be limited to, flanges and block valves

and sufficient pipeline from the Pipeline's

existing transmission facilities to the edge of

Pipeline's right-of-way. "M&R Equipment" shall

include miscellaneous connecting pipeline to the

tap, meters, compression, flow and pressure

regulators, filters/separators, gas heaters,

flanges, check valves, electronic gas measurement,

communication equipment and gas conditioning and

odorization equipment other than equipment

included in the Tap. "Lateral" shall mean any

transmission pipeline extension (other than a

mainline extension) built by Pipeline from an

existing transmission pipeline facility or new Tap

to deliver gas to or on behalf of one or more

Customers, including new delivery points and

enlargements or replacements of existing laterals.

"Construction" shall mean the construction,

modification, rearrangement or installation by

Pipeline or its designee of Requested Facilities

to perform any service, including any Requested

Facilities necessary for Pipeline to deliver gas

to, or measure any gas delivered to or on behalf

of any Customer requesting Pipeline's construction

of such facilities.

 

37.2 A party shall submit a request for facilities

under Section 11.A.1. requesting Pipeline to

construct Requested Facilities in conjunction with

a request for transportation services ("Requesting

Customer"). Notwithstanding the standards set

forth in Section 20 of these General Terms and

Conditions, Pipeline will receive and process all

such all such requests for construction of

Requested Facilities in a manner that is not

unduly discriminatory.

 

37.3 Pipeline shall construct Requested Facilities

under the conditions provided below:

A. Requested Facilities shall be located at points that,

in Pipeline's reasonable judgment, are the most practical,

convenient and readily accessible sites; provided, however,

Pipeline shall approve