Dominion Transmission, Inc.

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 09/01/2005, Docket: RP05-423-001, Status: Effective

Third Revised Sheet No. 1157 Third Revised Sheet No. 1157 : Effective

Superseding: Second Revised Sheet No. 1157


Capacity Release


23.6 Other Provisions (cont.)


C. No individual customer can hold more than 30 percent

of the capacity at any Receipt Point at which Pipeline

can receive 30,000 Dt per Day or more.


D. Pipeline will be indemnified and held harmless by

Releasing Customer and Replacement Customers for all

activities under this Section, except for costs

arising solely as direct result of Pipeline's

negligence or intentional malfeasance.