Dominion Transmission, Inc.

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 08/08/2005, Docket: RP05-507-000, Status: Effective

Third Revised Sheet No. 1154 Third Revised Sheet No. 1154 : Effective

Superseding: Second Revised Sheet No. 1154

GENERAL TERMS AND CONDITIONS

Capacity Release

 

23.5 Replacement Customers.

A. Replacement Customers hold the rights granted by Releasing Customer for service by

Pipeline to nominate quantities of service deliverable at Primary Points identified by

Releasing Customer, at the first available nomination opportunity upon consummation of

the release transaction for the effective date and time of the contract. Replacement

Customers may also use Secondary Points to the extent such points would otherwise be

available to Releasing Customer. After a permanent release, Replacement Customer may

request Primary point changes under the applicable procedures of Pipeline's FERC Gas

Tariff. If a release is not permanent, Replacement Customer may seek to change

Primary points under its Service Agreement, and thereby permanently alter the

applicable Service Agreement of Releasing Customer, only to the extent expressly

authorized by Releasing Customer in the posted notice. Requests to change Primary

points must comply with all applicable procedures of Pipeline's FERC Gas Tariff. In

any event, Primary Point changes are subject to the risk that either party will not be

able to return to the original Primary point(s). All Primary point changes are

subject to Pipeline's determination that firm capacity is available.

 

B. Replacement Customers may release the capacity entitlements that were obtained under

this Section, subject to the terms of the original release; provided, however, that

Replacement Customers that obtain capacity on a volumetric basis shall not be entitled

to re-release such capacity.

 

C. Replacement Customers are subject to all applicable provisions of:

 

1. Pipeline's FERC Gas Tariff,

2. the firm Service Agreement between Pipeline and Releasing Customer, and

3. each and every preceding release of the subject capacity.

 

23.6 Other Provisions.

 

A. Any party may post offers to acquire capacity on Pipeline's EBB, in accordance with

Section 26, below, for a period not to exceed ten (10) Business Days.

 

B. Recall Provisions.

 

1. Releasing Customer's rights to recall capacity shall be stated clearly in the

posted notice of a release, including recall notification period(s) and Business

Day recall notification restriction, if applicable. Purchase of gas by Releasing

Customer from Replacement Customer at the city gate shall not be deemed an

exercise of a recall provision.

 

2. Releasing Customer may recall capacity only by complying with the provisions set

forth below.