Capacity Release




23.1 Availability.


A. This Section 23 is available to all holders of firm

capacity rights for service from Pipeline ("Releasing

Customers"), authorized by Part 284 of the Commission's

regulations, including Storage Capacity received by

Customers in connection with conversions of firm sales

entitlements as part of the Settlement in Docket No.

RP88-211, and/or the restructuring of Pipeline's

services in Docket No. RS92-14, or any similar or

related proceeding.


B. Customers receiving firm service from Pipeline through

an individual certificate authorized under Section 7(c)

of the Natural Gas Act are not eligible to release such

service entitlements through this Section. Pipeline

will consider requests to convert such service to

service under Part 284 of the Commission's regulations,

on a case-by-case basis.


C. Except as provided for in Section 11A.4.G., above,

Customers may release capacity under this section only

to the extent that the Releasing Customer pays separate

reservation and usage charges for such entitlements, as