Dominion Transmission, Inc.

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/01/2001, Docket: RP01- 74-000, Status: Effective

First Revised Sheet No. 1098 First Revised Sheet No. 1098 : Effective

Superseding: Original Sheet No. 1098

GENERAL TERMS AND CONDITIONS

Appalachian Aggregation Points

 

transportation is on Pipeline's "wet gas" system, the

products extraction rates shall apply. If, however,

Pipeline's transmission facilities are used to provide

service and Pipeline delivers gas to Delivery Points

that are upstream of the Aggregation Point, then the

usage charges set forth under Rate Schedule IT, or the

Reservation and usage charges set forth under Rate

Schedule FT, shall also apply. All gas introduced into

any of Pipeline's facilities, including facilities

upstream of Pipeline's Appalachian Aggregation Points,

without an effective transportation Service Agreement

will be subject to the provisions of Section 29 of the

General Terms and Conditions of this Tariff

(Unauthorized Gas).

 

11E.4 Transportation from an Aggregation Point. Agreements

for the transportation of gas downstream from an

Aggregation Point may be executed under Rate Schedules

IT, MCS, FT or FTNN. Firm transportation service

agreements may specify Aggregation Points as either

Primary or Secondary points.

 

11E.5 Preexisting Firm Transportation Agreements. Any

Customer receiving firm transportation service under a

Service Agreement executed prior to November 1, 1992,

shall have the right to elect to keep the individual

Appalachian Receipt Points, as stated in the Service

Agreement executed as of such date, or may elect to

replace such points with one or more Aggregation Points.

 

11E.6 Allocation of Capacity at an Aggregation Point.

A. No single firm transportation Customer shall secure

more than 30 percent of the capacity downstream

from any one major Aggregation Point with capacity

of 30,000 Dt per day or more.

B. If total nominations behind each Aggregation Point

exceed the physical capacity at each Aggregation

Point, capacity shall be allocated in the same

manner as capacity at other Receipt Points.

 

C. Pipeline shall have no obligation to schedule

deliveries of gas to an Aggregation Point unless

Pipeline has received corresponding nominations for

receipt of such gas and confirmation that a

Customer will accept the gas at the Aggregation

Point for redelivery downstream.