GSS-II RATE SCHEDULE

General Storage Service, Section 7(c)

 

5.3 In the event Customer has failed to meet the minimum

turnover requirements of Section 8.7 below, Pipeline shall

retain the quantity of gas required by Section 35.3.D of

the General Terms and Conditions.

 

5.4 Notwithstanding the provisions of Sections 5.1-5.3, for any

Day during the Summer Period that a Customer gives Pipeline

both (a) notice under Section 7 of this Rate Schedule for

injections into storage, and (b) notice under Section 8 of

this Rate Schedule for withdrawals from storage, to the

extent that quantities tendered for injection and the

quantities requested to be withdrawn are equal and such

quantities are redelivered by Pipeline at the same

injection/withdrawal point for subsequent transportation,

the injection/withdrawal charges in Section 5.1 above shall

not apply. Instead, there shall be a Usage Charge of $0.01

per dekatherm times the quantity of gas tendered for

injection plus $0.01 per dekatherm times the quantity of

gas requested for withdrawal. To the extent that such

quantities tendered for injection and requested for

withdrawal are not equal, the injection/withdrawal charges

reflected on the currently effective Sheet No. 35 shall

apply to the net difference.

 

5.5 Notwithstanding the general provision of Sections 4 and

5.1, above, if Pipeline and Customer mutually agree to

negotiated rates for service hereunder, such negotiated

rates shall apply in lieu of the otherwise applicable

charges identified in Sections 5.1.A through 5.1.E of this

Rate Schedule.

 

6. MINIMUM MONTHLY BILL

 

Unless Pipeline and Customer agree otherwise as provided in

Section 5.5, above, the minimum monthly bill shall be the sum of

the Storage Demand Charge and the Storage Capacity Charge, and

any other applicable charges as set forth in the General Terms

and Conditions of Pipeline's Tariff; plus any applicable

Reservation Charges as described in Section 5.1.H. above.