GSS-II RATE SCHEDULE
General Storage Service
injections exceed the Customer's daily entitlements.
Pipeline shall endeavor to inject on any one Day, as
much of Customer's storage nominations for such Day as
operating conditions will permit. If the total of all
nominations for storage injection for such Day
together with Pipeline's injections into storage under
Rate Schedule FTNN exceed the total quantity which
Pipeline can inject or cause to be injected into
storage on such Day, then the nominations for
additional injections such Day shall be allocated pro
rata at each storage injection Receipt Point, based
upon Customer's actual confirmed nomination to tender
gas for injection gas at that Receipt Point.
C. Maximum Daily Injection Quantity. The maximum daily
injection quantity for Customer shall be the sum of
Customer's daily injection entitlement as set forth in
Section 7.4.A above, plus any additional injection
quantities Pipeline has agreed to accept pursuant to
Section 7.4.B above.
7.5 Winter Period Injections.
A. Unless provided otherwise in Customer's Service
Agreement, during the Winter Period, Customer may
tender to Pipeline quantities up to one two- hundred
fourteenth (1/214th) of Customer's Storage Capacity
for injection into storage, unless Pipeline has issued
an operational flow order in accordance with Section
11B of the General Terms and Conditions, governing
Winter Period injections. This limitation upon daily
injections is subject to the tolerance levels set
forth in Section 35.3.A of the General Terms and
Conditions.
B. While such operational flow order is in effect:
1. From time to time, Pipeline may post, on its
Electronic Bulletin Board ("EBB"), Receipt Points
where Customer may tender quantities for
injection and any conditions applicable to
injection through such Receipt Points.
2. Pipeline may limit or refuse to accept injections
not tendered in accordance with the operational
flow order and EBB notice, unless Pipeline has
expressly agreed in the executed Service
Agreement to accept specific quantities at
specified points on a firm basis during the
Winter Period.