GSS-II RATE SCHEDULE
General Storage Service
F. Any Applicable Penalties. For excess daily injection
overruns, injections in excess of Storage Capacity,
and excess withdrawals, as required by Section 35.3 of
the General Terms and Conditions.
G. Any other applicable rates, charges, and penalties as
set forth in the General Terms and Conditions.
H. Additionally, for natural gas transported to Customers
under this Rate Schedule who have agreed to pay
additional charges based upon Pipeline's joint
ownership with Texas Eastern of transmission
facilities effectuating delivery at the Chambersburg
Delivery Point, Customer shall pay Pipeline each month
the applicable charges per Dt as set forth in the
then-effective Sheet Nos. 32 and 33 of this Tariff
(FT-GSS-II).
5.2 Fuel Retention. Pipeline will retain the percentage of gas
received for injection set forth on Sheet No. 35 as the
Storage Service Fuel Retention Percentage.
5.3 In the event Customer has failed to meet the minimum
turnover requirements of Section 8.7 below, Pipeline shall
retain the quantity of gas required by Section 35.3.D of
the General Terms and Conditions.
5.4 Notwithstanding the provisions of Sections 5.1-5.3, for any
Day during the Summer Period that a Customer gives Pipeline
both (a) notice under Section 7 of this Rate Schedule for
injections into storage, and (b) notice under Section 8 of
this Rate Schedule for withdrawals from storage, to the
extent that quantities tendered for injection and the
quantities requested to be withdrawn are equal and such
quantities are redelivered by Pipeline at the same
injection/withdrawal point for subsequent transportation,
the injection/withdrawal charges in Section 5.1 above shall
not apply. Instead, there shall be a Usage Charge of $0.01
per dekatherm times the quantity of gas tendered for
injection plus $0.01 per dekatherm times the quantity of
gas requested for withdrawal. To the extent that such
quantities tendered for injection and requested for
withdrawal are not equal, the injection/withdrawal charges
reflected on the currently effective Sheet No. 35 shall
apply to the net difference.