Dominion Transmission, Inc.
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 12/04/2008, Docket: RP09-53-000, Status: Effective
Original Sheet No. 367 Original Sheet No. 367
GSS-E RATE SCHEDULE
General Storage Service - Expansion
9. AUTHORIZED OVERRUNS
9.1 Authorized Withdrawal Overruns. Customer may request Pipeline to
deliver gas to Customer on any Day in addition to the quantity that
Customer is entitled to withdraw, as established pursuant to Section 8
of this Rate Schedule, and Pipeline will make such delivery if such gas
is available from Customer's Storage Gas Balance, unless Pipeline
issues an OFO pursuant to Section 11B.3.E. of the General Terms and
Conditions because, in Pipeline's sole judgment, such delivery cannot
be made without adverse effect upon deliveries to other Customers or to
Pipeline's other operations.
9.2 Authorized Injection Overruns. Customer may request Pipeline to
receive gas from Customer on any Day in addition to the quantity that
Customer is entitled to inject, as established pursuant to Section 7 of
this Rate Schedule, and Pipeline will accept such quantities if space
is available within Customer's Storage Capacity, unless in Pipeline's
sole judgment, capacity is not available or such receipt cannot be made
without adverse effect upon service to other Customers or to Pipeline's
other operations.
9.3 Authorized Capacity Overruns. Customer may request Pipeline to receive
gas from Customer on any Day in addition to the quantity that Customer
is entitled to store, as established in Customer's Service Agreement,
and Pipeline will accept such quantities unless, in Pipeline's sole
judgment, capacity is not available or such receipt cannot be made
without adverse effect upon service to other Customers or to Pipeline's
other operations.
9.4 For all quantities of gas delivered under the provisions of this
Section, unless Pipeline and Customer agree otherwise, Customer shall
pay Pipeline at the rate per Dt set forth at the currently effective
Sheet No. 35 of this Tariff for authorized overruns.
9.5 Service under the provisions of this Section shall be equal in
scheduling priority to service provided under the provisions of
Pipeline's Rate Schedule ISS.
10. GENERAL TERMS AND CONDITIONS
The General Terms and Conditions of this Tariff, and any revisions
thereof that may be proposed and made effective from time to time
hereafter, to the extent not inconsistent with the provisions of this
Rate Schedule, shall apply to and are made a part of this Rate
Schedule.