FT RATE SCHEDULE
Firm Transportation Service
5.3 Pipeline may elect to offer to transport at a rate that is
below the maximum but no less than the minimum rates set
forth on Sheet Nos. 32, 33, and 37 as applicable to this
Rate Schedule. However, Pipeline is not obligated to
offer to transport gas at any rates less that the maximum
rates.
5.4 Small Customers that comply with the conditions set forth
in Section 10, below, are eligible for a one-part rate
that shall be designated as the FT(SC) rate on Pipeline's
tariff sheets. The one-part rate shall be calculated to
substitute for the Reservation Charge and the Usage
Charge, identified in Section 5.1 above, but shall not
excuse Customer from payment of any of the other charges
identified in this Section 5 or the General Terms and
Conditions of this Tariff.
5.5 Notwithstanding the general provision of Sections 4 and
5.1, above, if Pipeline and Customer mutually agree to
negotiated rates for service hereunder, such negotiated
rates shall apply in lieu of the otherwise applicable
charges identified in Sections 5.1.A through 5.1.E of this
Rate Schedule.
6. RECEIPTS AND DELIVERIES
6.1 Each executed Service Agreement shall specify Primary
Receipt and Primary Delivery Points.
A. Each executed Service Agreement shall specify the
maximum quantities that Pipeline is obligated to
receive on any Day at each Primary Receipt Point.
Pipeline shall also receive, at the Receipt Point(s),
a quantity for fuel retention. Under the executed
Service Agreement, the sum of the quantities
specified at each Primary Receipt Point shall not
exceed the MDTQ.
B. Each executed Service Agreement may state the maximum
quantities that Pipeline is obligated to deliver on
any Day at each Primary Delivery Point. This
quantity shall be Pipeline's Maximum Daily Delivery
Obligation ("MDDO") at each point.