Original Sheet No. 102 Original Sheet No. 102 : Effective
USS RATE SCHEDULE
Unbundled Sales Service
7.2 In the event Pipeline is advised by a Customer that,
absent adjustment of the curtailment level contemplated
by Section 7, a Customer will be unable to render service
to the priority-use requirements specified in Sections
401 and 402 of the Natural Gas Policy Act of 1978
("NGPA") and 18 C.F.R. Section 281.201 et seq. of the
Commission's Regulations ("high priority-use
requirements") or is advised by a Customer that
adjustment of the curtailment level is necessary to avoid
irreparable injury to life or property (including
environmental emergencies) or to provide for minimum
plant protection ("emergency situation"), then Pipeline
shall adjust its curtailment of all other Customers on a
pro rata basis as necessary to deliver the quantities
required to avoid or mitigate the impact on the "high
priority-use requirements" or the "emergency situation."
While Pipeline will make adjustments in curtailment
promptly upon notification by Customer, Customer must
provide Pipeline within 24 hours of notification a sworn
statement attesting:
A. that all sources of gas supply available to
Customer, including peak-shaving and storage, were
and are being utilized to the maximum extent
possible during the time period for which the
exception to the curtailment provisions of Section 7
is in effect; and
B. that all interruptible services of Customer were and
are being interrupted or curtailed during the time
period for which the exception to the curtailment
provisions of Section 7 is in effect; and
C. that no alternate fuel could be utilized or is
available to be utilized to prevent the necessity
for an exception to the curtailment provisions of
Section 7.
7.3 Pipeline shall not be liable for granting exceptions to
the curtailment provisions of Section 7 for any Customer
based upon a request submitted by any such Customer to
Pipeline under the "high priority-use requirements" and
"emergency situation" relief provisions of this Section
7. In the event that Customer does not provide the sworn
statement on a timely basis as required by this Section
7, then all quantities attributable to the adjustments