Cotton Valley Compression LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2000, Docket: CP99-541-003, Status: Effective
Original Sheet No. 7 Original Sheet No. 7 : Effective
(ii) Base rates and the deferred account surcharge rates will reflect the
changed capacity of any new leased compressor(s), with the capacity
billing determinant equal to the higher of actual capacity of the
compressor or firm contract demand levels.
4. MONTHLY BILL
(a) The bill for deliveries during each billing period under this rate schedule
shall be calculated using the applicable Reservation Charge, the applicable
Commodity Charge, and the applicable surcharges.
(b) The bill shall include any scheduling and balancing charges or penalties
determined pursuant to Article 9 and 10 of the General Terms and Conditions.
5. RESERVATION CHARGE CREDITS
If, except for reasons of force majeure, CVC is unable to deliver during any one or
more days the quantity of natural gas which Shipper delivers to CVC and desires to
transport from primary receipt points to primary delivery points, up to the MDTQ,
then the Reservation Charge as otherwise determined shall be reduced by an amount
equal to the difference between the quantity of natural gas actually delivered on
the day(s) involved and the quantity of natural gas, up to the MDTQ, which Shipper
in good faith demanded to receive on such day(s) times the applicable Reservation
Rate and Reservation Surcharges stated on a daily basis.
6. GENERAL TERMS AND CONDITIONS
All of the General Terms and Conditions as effective from time to time, are
applicable to this rate schedule and hereby made a part hereof.
7. OPERATIONAL FLOW ORDERS
CVC shall not issue operational flow orders (OFOs) to firm shippers because of a
lack of installed compression capacity below firm contracted levels, as would occur
if and when CVC exercised its certificated authority to reduce compression
horsepower to respond to reduced service demand.