Columbia Gulf Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2003, Docket: RP03-447-000, Status: Effective
Third Revised Sheet No. 129A Third Revised Sheet No. 129A : Effective
Superseding: Second Revised Sheet No. 129A
GENERAL TERMS AND CONDITIONS (Continued)
(d) "Intraday 2 Nomination Cycle" is 5:00 p.m. for nominations leaving control of the nominating
party; 5:15 p.m. for receipt of nominations by the Transporter (including from TTTSPs); 5:30 p.m. to send
Quick Response; 8:00 p.m. for receipt of completed confirmations by Transporter from upstream and downstream
connected parties; 9:00 p.m. for Transporter to provide scheduled quantities to affected Shippers and
Interconnecting Operators, and to provide scheduled quantities to bumped parties (notice to bumped parties),
(central clock time on the Gas Day). Scheduled quantities resulting from Intraday 2 Nominations should be
effective at 9:00 p.m. on Gas Day. Bumping is not allowed during the Intraday 2 Nomination Cycle.
(e) For purposes of (b), (c) and (d) above, "provide" shall mean, for transmittals pursuant to
standards 1.4.x, receipt at Shipper's or Interconnecting Operator's designated site, and for purposes of
other forms of transmittal, it shall mean send or post.
1.26 "OBA" shall mean Operational Balancing Agreement between two parties which specifies the procedure for
managing operating variances at an interconnect.
1.27 "Offsystem-Onshore Facilities" or "Offsystem-Onshore Zone" shall mean the following facilities generally
described as follows: Apple Springs (15.7 miles of 8-inch, 2.7 miles of 6-inch, and 4.9 miles of 4-inch
pipeline, with one 3-inch meter and two 4-inch meters located in Angelina and Trinity Counties, Texas),
Arkansas-Oklahoma (5.4 miles of 8-inch, 2.0 miles of 6-inch, and 2.8 miles of 4-inch pipeline, with eight 3-
inch meter runs and one 4-inch meter run located in Sebastian and Logan Counties, Arkansas), Bonus Field-
Wharton County (1.9 miles of 4-inch pipeline and three meter stations located in Wharton County, Texas), Carson
Dome (9.95 miles of 12-inch pipeline, with one 4-inch meter station located in Jefferson Davis County,
Mississippi), Carter Creek (10.0 miles of 22-inch pipeline which ties into the 36-inch Overthrust pipeline
segment located in Uinta County, Wyoming), Cut-off (1.7 miles of 10-inch, 2.8 miles of 8-inch, and 0.8 miles of
6-inch pipeline, with one dual 6-inch meter run measurement station located in Lafourche Parish, Louisiana),
Irion County (17.9 miles of 6-inch pipeline, 1-730 HP compressor, 1-620 HP compressor, seven 2-inch meters, and
two 3-inch meters, located in Irion County, Texas), and Moore Sams-Jumonville (1.3 miles of 6-inch and 0.4
miles of 4-inch pipeline, with one 6-inch meter run and one 4-inch meter run located in Pointe Coupee Parish,
Louisiana).