Columbia Gas Transmission LLC
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2009, Docket: RP09-792-002, Status: Pending
Ninth Revised Sheet No. 28 Ninth Revised Sheet No. 28
Superseding: Eighth Revised Sheet No. 28
Currently Effective Rates
Applicable to Rate Schedule SST and GTS
Rate Per Dth
Transportation Cost Electric Power Annual Total
Base Rate Adjustment Costs Adjustment Charge Effective Daily
Tariff Rate Current Surcharge Current Surcharge Adjustment Rate Rate
1/ 2/
Rate Schedule SST
Reservation Charge 3/ 4/$ 5.442 0.341 0.040 0.042 0.002 - 5.867 0.1929
Commodity
Maximum ¢ 1.02 0.23 0.04 0.58 0.08 0.19 2.14 2.14
Minimum ¢ 1.02 0.23 0.04 0.58 0.08 0.19 2.14 2.14
Overrun 4/ ¢ 18.91 1.35 0.17 0.72 0.09 0.19 21.43 21.43
Rate Schedule GTS
Commodity
Maximum ¢ 74.77 2.47 0.30 0.86 0.09 0.19 78.68 78.68
Minimum ¢ 3.08 0.35 0.30 0.68 0.09 0.19 4.69 4.69
MFCC ¢ 71.69 2.12 0.00 0.18 0.00 - 73.99 73.99
1/ Excludes Account 858 expenses and Electric Power Costs which are recovered through Columbia's Transportation Costs Rate Adjustment (TCRA)
and Electric Power Costs Adjustment (EPCA), respectively. For rates by function, see Sheet No. 35.
2/ ACA assessed where applicable pursuant to Section 154.402 of the Commission's Regulations.
3/ Minimum reservation charge is $0.00.
4/ In addition to the above reflected Base Tariff SST Demand Rate, shippers utilizing the Eastern Market Expansion (EME) facilities for Rate Schedule SST service will
pay an additional demand charge of $12.201 per Dth per month, for a total SST reservation charge of $17.643. If EME customers incur an overrun for SST services
that is provided under their EME Project service agreements, they will pay an additional 40.11 cents for such overruns, for a total overrun rate of 59.02 cents.
The applicable EME demand charge and EME overrun charge can be added to the Total Effective Rate above to calculate the EME Total Effective Rates.