Colorado Interstate Gas Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/01/2010, Docket: RP10-689-000, Status: Effective

Second Revised Sheet No. 374A Second Revised Sheet No. 374A

Superseding: First Revised Sheet No. 374A

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

13.3 (continued)

(d) When transportation service occurs within the Northeast

Colorado Storage System which is Kit Carson Station to

Watkins Station and Fort Morgan to Watkins Station.

 

(e) When Transportation service occurs in the No-Fuel Wheeling

Area which is located on Transporter's Uinta and Parachute

Creek Laterals. The No-Fuel Wheeling area shall consist of

the facilities between the Anabuttes Meter Station and the

Greasewood Compressor Station on the Uinta Lateral and

between the PSCo Rifle Plant and the Greasewood Compressor

Station on the Parachute Creek Lateral. Transportation

occurring within the No-Fuel area that involves high pressure

receipts and lower pressure deliveries will be eligible for

the No-Fuel Wheeling Reimbursement Percentage if the

transaction does not require Transporter compression in order

to receive or deliver Gas.

 

(f) When transportation service occurs between Transporter's

Enterprise North Point of Receipt and the inlet of the Box

Elder Point of Delivery.

 

(g) When transportation service occurs between Transporter's Blue

Forest Point of Receipt and its Alkali Pond Point of

Delivery.

 

13.4 Fuel Reimbursement calculations shall be accomplished pursuant to

NAESB WGQ Standards.

 

(a) Fuel Reimbursement calculation shall be rounded to the

nearest Dth for each Nomination transaction.

 

(b) Balanced Nomination transactions are calculated as follows:

Receipt Quantity times (1-(Fuel Reimbursement

Percentage/100)) equals Delivery Quantity.

 

(c) In the event of differences resulting from rounding the

calculation of Fuel Reimbursement, a Nomination shall not be

rejected for differences less than 5 Dth (NAESB WGQ Standard

1.3.29).

 

(d) Fuel Reimbursement quantities have the same scheduling

priority as their base Nomination (NAESB WGQ Standard

1.3.31).