Colorado Interstate Gas Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2010, Docket: RP10-689-000, Status: Effective
Tenth Revised Sheet No. 352 Tenth Revised Sheet No. 352
Superseding: Ninth Revised Sheet No. 352
GENERAL TERMS AND CONDITIONS
(Continued)
10.4 (b) continued
quantities that are scheduled including Rate Schedule NNT-1
quantities scheduled at Secondary Points shall be allocated
first and Rate Schedule NNT-1 quantities that are not scheduled
shall be allocated thereafter. If there is more than one Rate
Schedule NNT-1 Agreement Delivering Gas at a Primary Point(s)
of Delivery, the Rate Schedule NNT-1 quantities shall be
allocated at each Primary Point of Delivery pro rata based on
that Primary Point of Delivery Quantity designated in the
Agreement.
(c) At Points of Delivery where Hourly Services are provided,
Transporter shall use the same allocation method for Hourly
Deliveries as is used for Daily allocations. Hourly Services
are not provided at Points of Receipt, therefore, hourly
allocations and any related charges are not applicable to
Points of Receipt.
(d) All transaction activities at points of interconnection with
other interstate or intrastate pipelines shall be allocated
such that the hourly quantities are 1/24 of the daily allocated
quantities, unless the interconnecting party has a mechanism in
place allowing for uneven hourly deliveries.
(e) The timing for reporting daily operational allocations after
the Gas has flowed is within one Business Day after end of Gas
Day. If the best available data for reporting daily operational
allocations is the scheduled quantity, that quantity should be
used for the daily operational allocation (NAESB Standard
2.3.21).