3.4 Failure to Meet Specifications. In the event that Gas Tendered
hereunder fails to meet the specifications in Section 3.1 and
Transporter has not agreed to accept gas pursuant to Sections 3.2 or
3.3, the measuring Party shall notify the other Party of such
failure. Transporter may refuse to accept such Gas. The Party
Tendering such Gas hereunder shall indemnify the receiving Party for
any injury, damage, loss, or liability caused by such Gas, except to
the extent Transporter knowingly and willingly accepts such Gas.
3.5 Specification of Gas Delivered or Received on the Valley Line and/or
through the Supporting Air Blending Operations.
(a) All Gas Delivered by Transporter on the Valley Line may be
blended with air and shall be at an input factor (heating value
divided by the square root of the specific gravity) of 1,200,
plus or minus 6.2 percent. However, should situations occur on
an hourly basis such that Transporter is unable to maintain the
input factor within the above-specified range, Shippers agree
to extend such ranges up to 1200 plus or minus 7.8 percent to
allow required quantities to be Delivered. Transporter will
endeavor to keep such occurrences to a minimum and to return