Colorado Interstate Gas Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2010, Docket: RP10-689-000, Status: Effective
Fifth Revised Sheet No. 231B Fifth Revised Sheet No. 231B
Superseding: Fourth Revised Sheet No. 231B
GENERAL TERMS AND CONDITIONS
(Continued)
1.36 "Hour" shall mean the 60-minute period beginning at the top of each
hour of the Gas Day and ending at the top of the next hour (i.e.
Hour 1 starts at 8:00 a.m. CCT and ends at 9:00 a.m. CCT).
1.37 "Hourly Entitlement Enhancement Nomination" or "HEEN" shall mean a
request submitted for the Timely or Evening Nomination Cycles under
Rate Schedule TF-1 or TF-4 by a Shipper for a prospective
Transportation transaction from a Point of Receipt to a Qualified
Point of Delivery. Further, the flow path for such Nomination must
be forward haul through at least two of the Hourly Entitlement
Enhancement Nomination Compressor Stations as listed on
Transporter's Information Postings Web Site. An Hourly Entitlement
Enhancement Nomination may be used to reserve capacity to support
non-uniform Hourly Deliveries as specified in Shipper's
Transportation Service Agreement ("TSA"). Hourly Entitlement
Enhancement Nominations must meet all other criteria for a valid
Nomination. However, the sum of all HEENs under an Agreement may not
be in excess of the Shipper's MDQ. An Hourly Entitlement Enhancement
Nomination may also be Delivered to an NNT Balancing Point. The
Scheduled Quantities for an Hourly Entitlement Enhancement
Nominations shall be distributed pro rata based on the Shipper's
firm capacity entitlements under the TSA at the related Primary
Points of Delivery.
1.38 "Injection Period" shall consist of the period commencing on May 1
of any year and continuing through October 31 of such year for CIG
Mainline Storage, the period commencing on June 1 of any year and
continuing through October 31 of such year for Young Storage and the
period commencing on June 1 of any year and continuing through
October 31 of such year for Totem Storage.
1.39 "Interconnecting Party" shall mean the Party or such Party's
designee that is responsible for operations of a natural Gas system
which interconnects with Transporter's pipeline system and is
responsible for verifying Nominations and scheduling Gas flow at
such Points of interconnections. An Interconnecting Party is also a
Confirming Party. Each Interconnecting Party is required to conform
to the schedules set forth in Section 6 of these General Terms and
Conditions of this Tariff, unless specifically exempted by
Transporter.
1.40 "Intraday Nomination" shall mean a Nomination submitted by a
Nominating Party after the Timely Nomination deadline set forth in
Section 6 of these General Terms and Conditions. Intraday
Nominations shall be accepted for the following cycles pursuant to
the schedule set forth in Section 6 of these General Terms and
Conditions: