Colorado Interstate Gas Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2010, Docket: RP10-689-000, Status: Effective
First Revised Sheet No. 75P First Revised Sheet No. 75P
Superseding: Original Sheet No. 75P
RATE SCHEDULE NNT-1
NO-NOTICE STORAGE AND TRANSPORTATION SERVICE - FIRM
(Continued)
4.4 Hourly Unauthorized Overrun (continued)
(a) Transporter will first evaluate hourly deliveries and peak hour
rights at each delivery location using non-coincident peak hour
deliveries.
(b) Should an hourly overrun be indicated from this first step, a
second evaluation will be performed to determine the delivery
load for each hour under the Agreement using the coincident
hourly delivery quantities for all locations.
(i) Hourly overrun charges will only be assessed if an hourly
overrun is determined based on the coincident peak delivery
calculation.
(ii) Should an unauthorized hourly overrun occur, Shipper shall
pay the higher of 1) an amount obtained by multiplying the
Hourly Unauthorized Overrun Rate times the largest quantity
of such Hourly Unauthorized Overrun Gas during any one Hour
of a Day, or 2) an amount obtained by multiplying the
Hourly Unauthorized Overrun Rate times 24, times the excess
quantity of the Three Hour Peak, as defined in Rate
Schedule NNT-1 Section 2.2.
4.5 Shipper shall pay only one daily authorized overrun charge when
Shipper's authorized injection overruns also result in an authorized
storage capacity overrun. Shipper shall pay the higher of the Daily
Authorized Injection Overrun charge, calculated pursuant to Section
4.2(a) above, or the Daily Authorized Storage Capacity Overrun
charge, calculated pursuant to Section 4.2(c) above.