RATE SCHEDULE NNT-1

NO-NOTICE STORAGE AND TRANSPORTATION SERVICE - FIRM

(Continued)

 

 

4.4 Hourly Unauthorized Overrun (continued)

 

(a) Transporter will first evaluate hourly deliveries and peak hour

rights at each delivery location using non-coincident peak hour

deliveries.

 

(b) Should an hourly overrun be indicated from this first step, a

second evaluation will be performed to determine the delivery

load for each hour under the Agreement using the coincident

hourly delivery quantities for all locations.

 

(i) Hourly overrun charges will only be assessed if an hourly

overrun is determined based on the coincident peak delivery

calculation.

 

(ii) Should an unauthorized hourly overrun occur, Shipper shall

pay the higher of 1) an amount obtained by multiplying the

Hourly Unauthorized Overrun Rate times the largest quantity

of such Hourly Unauthorized Overrun Gas during any one Hour

of a Day, or 2) an amount obtained by multiplying the

Hourly Unauthorized Overrun Rate times 24, times the excess

quantity of the Three Hour Peak, as defined in Rate

Schedule NNT-1 Section 2.2.

 

4.5 Shipper shall pay only one daily authorized overrun charge when

Shipper's authorized injection overruns also result in an authorized

storage capacity overrun. Shipper shall pay the higher of the Daily

Authorized Injection Overrun charge, calculated pursuant to Section

4.2(a) above, or the Daily Authorized Storage Capacity Overrun

charge, calculated pursuant to Section 4.2(c) above.