Eastern Shore Natural Gas Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/01/2009, Docket: RP09-337-001, Status: Effective
Sub 2nd Revised Sheet No. 193E Sub 2nd Revised Sheet No. 193E
Superseding: Sub First Revised Sheet No. 193E
EASTERN SHORE NATURAL GAS COMPANY
GENERAL TERMS AND CONDITIONS
(Continued)
29. Capacity Release (Continued)
(g) Awarded Bids (Continued)
(4) The rate charged for the capacity.
(5) All conditions of release objectively stated
including, but not limited to, any recall or reput
conditions.
(6) The applicable Rate Schedule, specific quantity
of capacity released, the Point of Receipt, and the
Delivery Point Area.
(h) Capacity Releases Not Subject to Prior Notice or Competitive
Bidding
(1) For Prearranged Releases (i) of thirty-one (31) days
or less at any mutually agreed upon rate, (ii)
of greater than one (1) year at maximum tariff
rates, (iii) to an asset manager as defined in Section
29(h)(3), or (iv) to a marketer participating in a
state-regulated retail access program as defined in
Section 29(h)(4), a Firm Shipper releasing capacity to
a qualified Replacement Shipper need not comply with the
notification and bidding requiremens of Section 29(i).
Notice of a firm release under this paragraph must be
provided on TSP?s IWS as soon as possible, but not later
than the first nomination, after the release transaction
commences.
(2) When a release of capacity for thirty-one (31) Days
or less is exempt from bidding requirements under
Section 29(h)(1), a Firm Shipper may not roll-over,
extend, or in any way continue the release to the same
Replacement Shipper using the 31 days or less bidding
exemption until 28 days after the first release period
has ended. The 28-day hiatus does not apply to any re-
release to the same Replacement Shipper that is posted
for bidding or that qualifies for any of the other
exemptions from bidding in Section 29(h)(1).