Eastern Shore Natural Gas Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2002, Docket: RP00-393-002, Status: Effective
Second Revised Sheet No. 171 Second Revised Sheet No. 171 : Effective
Superseding: First Revised Sheet No. 171
EASTERN SHORE NATURAL GAS COMPANY
GENERAL TERMS AND CONDITIONS
(Continued)
24. Operational Flow Orders (Continued)
(b) Pipeline-Specific Operational Standards for Issuance of
OFOs (Continued)
(1) (Continued)
rate schedules be made on a basis consistent with
the flow rate and limitations set forth in the
OFO. Such OFO shall be limited to the smallest
practicable segment of Seller's pipeline system.
For the duration of the OFO, increases in
scheduled delivery quantities within affected
segments of Seller's pipeline will be made on a
prospective basis only.
(2) Seller may issue an OFO directing a Buyer to take
specific actions to enable Seller to adequately
respond to certain operational conditions
occurring on Seller's pipeline system, including,
but not limited to:
(a) Partial or entire electronic failure that
impairs Seller's ability to monitor and
control Seller's essential facilities.
(b) Mechanical or physical failure that affects
Seller's ability to transport gas, including
but not limited to, pipeline failure,
compressor failure, regulator failure or
other similar mechanical or physical failure.
(c) External operations such as highway
construction operations that may require
Seller to reduce operating pressures in, or
remove from service, a portion of Seller's
pipeline facilities.
(d) Loss of natural gas supply from third-party
upstream transporters due to emergencies
occurring on such upstream transporter's
systems.