Eastern Shore Natural Gas Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/1997, Docket: CP96-128-004, Status: Effective
Original Sheet No. 118 Original Sheet No. 118 : Effective
EASTERN SHORE NATURAL GAS COMPANY
GENERAL TERMS AND CONDITIONS
(Continued)
12. Construction of Facilities (Continued)
(d) (Continued)
(1) (Continued)
(iii) The estimated capital cost of the proposed
facilities, assumed to be depreciated over the
life of the proposed new service; and,
(iv) A carrying charge on all capital costs for the
proposed facilities equal to the pre-tax
overall rate of return reflected in Seller's
most recent rate filing.
(2) The facilities will be adequate to provide the
requested service and the utilization of the
facilities will not, in Seller's reasonable
judgment, compromise the integrity of Seller's
pipeline system.
(3) The necessary authorizations are obtained from
governmental bodies.
(e) Seller may waive the requirement for its ownership of any
facilities based on the determination that the best
interests of Buyer and Seller are served by the granting
of such waiver. Waivers of Seller's requirement for its
ownership of any facilities will be granted in a not
unduly discriminatory manner based on an evaluation of
the potential costs and revenues related to the
facilities, other relevant economic factors and operating
considerations.
(f) Seller shall not be obligated to build or contribute to
the cost of building any new facilities or lateral
pipelines to provide service to any Buyer under this
Tariff. Nothing in Section 12 of these General Terms and
Conditions shall require Seller to file an application
for a Certificate of Public Convenience and Necessity