9. CAPACITY RELEASE PROGRAM (Continued)
9.6 Prearranged Releases. Shipper electing to release capacity on the
basis of a prearranged release must post notice on Transporter's EBB
pursuant to Section 9.8 herein.
(a) No open season is required for a prearranged release which
meets all of the terms of the release and is:
(i) a release for more than one Year at the maximum
reservation rate under the applicable Tariff rate schedule;
(ii) a release for any period of thirty-one Days or less;
(iii) a release to an asset manager as defined by FERC
regulations at 18 C.F.R. 284.8; or
(iv) a release to a marketer participating in a state-
regulated retail access program as defined by FERC
regulations at 18 C.F.R 284.8. All other prearranged
releases shall be subject to an open season requirement
contained in Section 9.5 hereof.
(b) A Releasing Shipper may not re-release capacity that is a
rollover or extension of a release of thirty-one Days or less
to the same Replacement Shipper until twenty-eight (28) Days
after the first release period has ended. The 28-Day hiatus
does not apply to any re-release to the same Replacement
Shipper that is posted for bidding or that qualifies for any
of the other exemptions from bidding in this Section 9.6.
(c) A Shipper electing to release capacity on a prearranged basis
not subject to an open season must post the notice of release
on Transporter's EBB or submit its notice via an EDI upload
utilizing the data sets included in the NAESB WGQ Standards
pursuant to the timeline for non-biddable releases in
Sections 9.5(c)(xii) - (xv).
(d) Any capacity release transactions effectuated during the
period between July 30, 2008 and November 21, 2008, shall be
grandfathered and shall not be required to comply with the
requirement of 18 C.F.R. 284.8(b)(2), that releases with a
rate greater than the maximum rate must take effect on or
before one year from the date on which the pipeline is
notified of the release.