GENERAL TERMS AND CONDITIONS
Unless otherwise stated, these General Terms and Conditions apply to all
transportation service provided under this Tariff.
1. DEFINITIONS
1.1 "Backhaul" - shall mean a transaction that is nominated opposite to
the Primary Receipt-to-Delivery Flow Path direction of a TSA.
Backhaul nominations are scheduled as Secondary Capacity up to the
MDQ.
1.2 "Bidding Shipper" - is any Shipper who is pre-qualified pursuant to
Section 9 of the General Terms and Conditions to bid for capacity
or who is a party to a prearranged release.
1.3 "British Thermal Unit" ("Btu") - One (1) Btu shall mean one British
thermal unit and is defined as the amount of heat required to raise
the temperature of one (1) pound of water from fifty-nine degrees
Fahrenheit (59°F) to sixty degrees Fahrenheit (60°F) at a constant
pressure of fourteen and seventy-three hundredths pounds per square
inch absolute (14.73 psia). Total Btu's shall be determined by
multiplying the total volume of Natural Gas delivered times the gas
Heating Value expressed in Btu's per cubic foot of gas adjusted on
a dry basis.
1.4 "Bumping" or "Bump" - shall mean:
(a) The reduction of a previously scheduled and confirmed
interruptible transportation quantity to permit Transporter
to schedule and confirm a firm transportation nomination
which has a higher priority and which was submitted as an
intraday nomination.
(b) In the event that a discount is granted pursuant to Section
3.2 of Rate Schedule FT that affects previously scheduled
quantities, "Bumping" or "Bump" shall also mean the reduction
of a firm transportation quantity previously scheduled and
confirmed to permit Transporter to schedule and confirm a
firm transportation intraday nomination which has a higher
priority.
(c) In the even of an intraday recall of released capacity,
"Bumping" or "Bump" shall also mean the reduction of the
Replacement Shipper's previously scheduled and confirmed firm
transportation quantity.