22.0 NOMINATIONS PROCEDURES (Cont'd)

 

22.3 Intra-Day Nominations (cont'd)

 

The Intraday 1 Nomination Cycle: 10:00 am for

nominations leaving control of the nominating party;

10:15 am for receipt of nominations by the transporter

(including from TTTSP's); 10:30 am to send Quick

Response; 1:00 pm for receipt of completed

confirmations by transporter from upstream and

downstream connected parties; 2:00 pm for Chandeleur

to provide scheduled quantities to affected shippers

and point operators, and to provide scheduled

quantities to bumped parties (notice to bumped

parties), (central clock time on the gas day).

Scheduled quantities resulting from Intraday 1

Nominations should be effective at 5:00 pm on gas day.

(NAESB WGQ 1.3.2(iii))

 

NOTE: Intraday bump notices shall indicate whether

daily penalties will apply for the gas day for which

quantities are reduced. (NAESB WGQ 1.3.51) Intraday

bump notices shall contain at least the affected

Service Requester Contract, Receipt and / or Delivery

Location, and Receipt and / or Delivery Point Quantity

from the Scheduled Quantity (NAESB WGQ 1.4.5).

(NAESB WGQ 5.3.40)

 

The Intraday 2 Nomination Cycle: 5:00 pm for

nominations leaving control of the nominating party;

5:15 pm for receipt of nominations by the transporter

(including from TTTSP's); 5:30 pm to send Quick

Response; 8:00 pm for receipt of completed

confirmations by Chandeleur from upstream and

downstream connected parties; 9:00 pm for Chandeleur

to provide scheduled quantities to affected shippers

and point operators (central clock time on the gas

day). Scheduled quantities resulting from Intraday 2

Nominations should be effective at 9:00 pm on gas day.

Bumping is not allowed during the Intraday 2

Nominations Cycle. (NAESB WGQ 1.3.2(iv))

 

For purposes of the above, "provide" shall mean, for

transmittals pursuant to NAESB WGQ standards 1.4.x,

receipt at the designated site, and for purposes of

other forms of transmittal, it shall mean send or

post. (NAESB WGQ 1.3.2(v))