Chandeleur Pipe Line Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/01/2003, Docket: RP03-220-000, Status: Effective
Original Sheet No. 54A Original Sheet No. 54A : Effective
GENERAL TERMS
AND CONDITIONS
12.0 FORCE MAJEURE
12.1 Force Majeure
Should either Shipper or Chandeleur be
rendered unable, wholly or in part, by force
majeure to carry out its obligations under the
Transportation Service Agreement, the obligations
of such Party, so far as they are affected by
force majeure, and the other Party's corresponding
obligations shall be suspended during the
continuance of any inability so caused, but for no
longer period, and such cause shall, so far as
possible, be remedied with all reasonable
dispatch. Where practical, the Party affected by
force majeure shall give notice of the occurrence
to the other.
12.2 Force Majeure Defined
(a) The term "force majeure," as
employed herein, shall mean acts of God,
strikes, lockouts or other industrial
disturbance, acts of the public enemy, wars,
blockades, insurrections, riots, epidemics,
landslides, lightning, earthquakes, fires,
storms, floods, high water, washouts, arrests
and restraints of governments and people,
civil disturbances, explosions, breakage or
accident to machinery or lines of pipe,
freezing of wells or lines of pipe, partial
or entire failure of Natural Gas wells, and
any other causes, whether of the kind herein
enumerated or otherwise, not reasonably
within the control of the Party claiming
suspension. Such term shall likewise
include: