Chandeleur Pipe Line Company

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 02/01/2003, Docket: RP03-220-000, Status: Effective

Second Revised Sheet No. 30 Second Revised Sheet No. 30 : Effective

Superseding: First Revised Sheet No. 30

 

 

GENERAL TERMS

AND CONDITIONS

 

 

6.0 SCHEDULING AND PRIORITY OF SERVICE (Cont'd)

 

6.6 "No Bump" Rule

 

Chandeleur will accept nominations for

interruptible service based on a "no bump" rule.

This rule provides that an interruptible agreement

under which gas is flowing at a receipt point

cannot be interrupted or "bumped" by an increased

(or new mid-month) nomination under an

interruptible agreement with a higher queue

position.