32. CONSTRUCTION OF FACILITIES

 

Any existing or potential Shipper may request a new interconnection on

Transporter's pipeline system, subject to the following conditions being met.

Transporter shall have no obligation to modify its existing facilities or

construct new facilities in order to receive or deliver Shipper's gas unless

otherwise ordered by the Commission. However, if a Shipper requests new or

additional transportation service and Transporter is agreeable to providing

the requested service it will do so on the following terms, unless otherwise

agreed to in writing, on a not unduly discriminatory basis:

 

A. If Transporter agrees to construct, own and operate lateral pipelines

(if applicable), metering and regulating facilities that include electronic

measurement and data communication equipment (if applicable) and/or new and/or

additional points of delivery to such Shipper or points of receipt from such

Shipper: (1) the metering and regulating facilities shall be installed at

point(s) which, in Transporter's reasonable judgment, is the most practical,

convenient and readily accessible location; (2) the lateral pipeline (if any)

shall be installed by use of not less than a nominal four-inch (4") diameter

pipe; (3) the Shipper will provide all exhibits necessary to support the

proposed service for any needed FERC proceedings and; (4) the Shipper will

contribute an aid-to-construction amount to Transporter which is equal to the

cost of the additional facilities including all costs involved in filing any

applications, pursuing said approvals, and in obtaining all licenses and

permits required for the services or construction and, further, amounts

necessary to reimburse any costs, including any income taxes that may be

incurred by Transporter as a result of the contribution. Transporter and

Shipper will agree on which party will construct and/or own and/or operate any

facilities to be constructed.

 

B. Shippers, whether new or existing, shall bear all costs and expenses

attributable to the construction of any lateral pipelines or expansions of

existing lateral pipelines. Nothing in this section shall require Transporter

to file an application for a certificate of public convenience and necessity

under Section 7.C of the Natural Gas Act seeking authorization to construct

any such facilities. Nothing in this section shall prevent Transporter from

contesting an application for service filed pursuant to Section 7(a) of the

Natural Gas Act. Transporter reserves the right to seek a waiver of the policy

set forth herein, for good cause shown, during any proceeding before the

Commission instituted under Section 7 of the Natural Gas Act.