Cheniere Creole Trail Pipeline, L.P.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 04/28/2008, Docket: RP08-137-000, Status: Effective

Original Sheet No. 127 Original Sheet No. 127 : Pending






Shipper shall provide gas flow commencement and termination dates on each

nomination. Once submitted, nominations, except for intra day nominations,

will remain in effect for the specified time period unless a prospective

electronic nomination change is received from Shipper or, in the case of an

interruptible Shipper, bumping as described in Section 10.A.2(c) herein



A Package ID is a way to differentiate between discrete business transactions.

When used, Package ID should be:


(a) supported for nominating and scheduling;

(b) mutually agreed between the applicable parties for allocations and

imbalance reporting;

(c) supported for invoicing (sales and purchase); and

(d) mutually agreed for transport invoicing.


Use of the Package ID is at the discretion of the service requestor, and if

sent, should be accepted and processed by the service provider.


2. Nomination Timeline


Transporter and Shipper shall support the following minimum NAESB standard

nomination cycles as set forth below in (a) and (b). Such nomination

opportunities shall represent the grid-wide synchronization times across the

North American pipeline network.


(a) Nominations for the Upcoming Gas Day


The Timely Nomination Cycle

(In Central Clock Time on the day prior to gas flow).


11:30 a.m. for nominations leaving control of the nominating party;

11:45 a.m. for receipt of nominations by Transporter;

12:00 p.m. to send Quick Response;

3:30 p.m. for receipt of completed confirmations by Transporter from

upstream and downstream connected parties;

4:30 p.m. for receipt of scheduled quantities by Shipper and point



Scheduled quantities resulting from Timely Nominations shall be effective on

the next Gas Day.