3. PRESSURE

 

Shipper shall deliver gas to Transporter at the pressure required from time to

time to enable the gas to enter Transporter's facilities at the Receipt

Point(s), but in no event shall such pressure exceed the maximum allowable

operating pressure of Transporter's system at such point(s). Transporter's

pipeline system is currently designed for a maximum allowable operating

pressure of 1440 psig, but may be subject to reduced maximum operating

pressures at certain locations pursuant to the requirements of regulatory

authorities.

 

Transporter shall deliver gas to Shipper or Shipper's designee at

Transporter's line pressure existing at the Delivery Point(s).