Caprock Pipeline Company
First Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/02/1998, Docket: RP99- 71-001, Status: Effective
Substitute Second Revised Sheet No. 38 Substitute Second Revised Sheet No. 38 : Effective
Superseding: Second Revised Sheet No. 38
SCHEDULING OF RECEIPTS AND DELIVERIES, cont.
thus, an intra-day nominator need not submit an hourly
nomination. Intra-day nominations should include an
effective date and time. The interconnected parties
should agree on the hourly flow of the intra-day
nomination, if not otherwise addressed in the Service
Agreement or Transporter's Tariff. All nominations,
excluding intra-day nominations, have rollover options.
Specifically, Shippers have the ability to nominate for
several days, months, or years, provided the
nomination begin and end dates are within the term of the
Shippers Service Agreement. Intra-day nominations do not
rollover nor do they replace the remainder of a standing
nomination. There is no need to re-nominate if an intra-
day nomination modifies an existing nomination. The total
receipt nominations less any Fuel Reimbursement Quantity
and other deductions must equal the equivalent thermal
quantity of either nominations for actual delivery or
delivery into an Aggregation Pool. Overrun volumes may be
nominated as a separate transaction.
16.3 CONFIRMATIONS
(a) Default confirmation procedures are as follows:
(i) With respect to the timely nomination/confirmation process at
a receipt or delivery point, in the absence of agreement to
the contrary, the lesser of the confirmation quantities will
be the confirmed quantity. If there is no response to a
Request For Confirmation or an unsolicited Confirmation
Response, the lesser of the confirmation quantity or the
previously scheduled quantity will be the new confirmed
quantity.