Caprock Pipeline Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/02/1998, Docket: RP99- 71-001, Status: Effective

Substitute First Revised Sheet No. 37A Substitute First Revised Sheet No. 37A : Effective

Superseding: First Revised Sheet No. 37A

 

GENERAL TERMS AND CONDITIONS, continued

 

 

(c) The Intra-day 1 Nomination Cycle: 10:00 a.m. for nominations

leaving control of the nominating party; 10:15 a.m. for receipt

of nominations by Transporter; 10:30 a.m. to send Quick

Response; 1:00 p.m. for receipt of completed confirmations by

Transporter from upstream and downstream connected parties; 2:00

p.m. for Transporter to provide scheduled quantities to affected

shippers and point operators, and to provide scheduled quantities

to bumped parties (notice to bumped parties), (central clock time

on the gas Day). Scheduled quantities resulting from Intra-day 1

Nominations should be effective at 5:00 p.m. on the gas Day.

 

(d) The Intra-day 2 Nomination Cycle: 5:00 p.m. for nominations

leaving control of the nominating party; 5:15 p.m. for receipt

of nominations by Transporter; 5:30 p.m. to send Quick Response;

8:00 p.m. for receipt of completed confirmations by Transporter

from upstream and downstream connected parties; 9:00 p.m. for

Transporter to provide scheduled quantities to affected shippers

and point operators (central clock time on the gas Day).

Scheduled quantities resulting from Intra-day 2 Nominations

should be effective at 9:00 p.m. on the gas Day. Bumping is not

allowed during the Intra-day 2 Nomination Cycle.

 

(e) For purposes of Section 16.1 (b)(c) and (d), “provide” shall

mean, for transmittals pursuant to standards 1.4.x, receipt at

the designated site, and for purposes of other forms of

transmittal, it shall mean send or post.

 

16.2 Include in the nomination the daily quantity of gas to

be received by Transporter (including Shipper's

transportation volumes and Btu levels, overrun

volumes, any volumes to satisfy past imbalances, and

any Fuel Reimbursement Quantity for volumes at each

specified Receipt Point), receipt points (primary

and/or secondary), Shipper defined beginning and

ending dates, and the daily quantity to be delivered

by Transporter at each specified delivery point

(primary and/or secondary) on the desired gas day, but

no sooner than the following day. All nominations,

including intra-day nominations, should be based on

daily quantity,