Carolina Gas Transmission Corporation
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/25/2009, Docket: RP09-296-000, Status: Effective
Original Sheet No. 166A Original Sheet No. 166A
Superseding: Original Sheet No. 166
applicable, the proposed rate for such release; and
(7) additional terms and conditions that are objective
and non-discriminatory.
(i) Posting of any capacity release meant to
implement an asset management agreement must
specify the volumetric level of the Replacement
Shipper’s delivery or purchase obligation and
the time periods during which that obligation
is in effect.
(b) Releases subject to bid also shall include the following:
(1) the expiration of the bid period, subject to the
applicable timeline in this Section 17;
(2) the minimum Reservation Rate;
(3) whether bids should be submitted in dollars and cents
or as a percentage of the Recourse Rate;
(4) the bid evaluation method; including the tie-break
method the Pipeline will apply to award capacity
among multiple bids that yield the same value. If
other than a first come, first serve method is
desired, the alternative bid evaluation method must
be set forth with sufficient specificity that the
Pipeline’s evaluation of the bids to determine the
“best bid” is a purely ministerial matter that does
not require any discretionary exercise of judgment by
the Pipeline.