Effective Date: 02/25/2009, Docket: RP09-296-000, Status: Effective

First Revised Sheet No. 166 First Revised Sheet No. 166

Superseding: Original Sheet No. 166

 

(c) The following releases need not comply with the bidding

requirements of Section 284.8, paragraphs (c) through (e)

of the Commission’s Regulations:

 

(1) A release of capacity to an asset manager as defined

in paragraph 284.8 (h)(3) of the Commission’s

regulations;

 

(2) A release of capacity to a marketer participating in

a state-regulated retail access program as defined in

paragraph 284.8 (h)(4) of the Commission’s

regulations;

 

(3) A release of capacity for more than one year at the

maximum tariff rate; and

 

(4) A release for any period of 31 days or less.

 

(d) When a release of capacity is exempt from bidding under

paragraph 284.8(h)(1)(iv) of the Commission’s regulations,

a firm shipper may not roll over, extend, or in any way

continue the release to the same Replacement Shipper using

the 31 days or less bidding exemption until twenty-eight

(28) days after the first release period has ended. The 28-

day hiatus does not apply to any re-release to the same

Replacement Shipper that is posted for bidding or that

qualifies for any of the other exemptions from bidding in

paragraph 284.8(h) (1) of the Commission’s regulations.

 

17.3 Offer of Capacity Release.

 

(a) A Releasing Shipper that desires to release all or part of

its capacity shall post the release on the Internet Website

by the posting deadline as determined under Section 17.4.

Such posting shall include terms and conditions of the

proposed release as follows:

 

(1) the releasing agreement;

 

(2) whether on a permanent or temporary basis;

 

(3) specifics of any recall or reput rights;

 

(4) the quantities to be released at specific locations

or segments;

 

(5) the period of the release;

 

(6) any Prearranged Replacement Shipper proposed to

obtain released capacity, including if the release is

to an asset manager or marketer participating in a

state-regulated retail access program and, if