Carolina Gas Transmission Corporation
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/01/2006, Docket: CP06- 71-001, Status: Effective
Original Sheet No. 133 Original Sheet No. 133 : Effective
(c) If no acceptable bids are submitted for any portion of the
capacity, Shipper will be entitled to continue its existing
service for any portion of the capacity, for any term
desired, provided Pipeline and Shipper agree to mutually
acceptable rates for the service at a level within the
range of posted maximum and minimum Tariff rates for the
applicable service, or at a mutually acceptable Negotiated
Rate for the applicable service. If Pipeline and Shipper
fail to agree on rates within 30 days of the bid close
date, Shipper’s Right of First Refusal will be deemed to
have terminated. If Shipper wishes to retain only a
portion of its capacity and Pipeline has indicated in the
special conditions of its posting that it has determined
that partial use or segmentation of the posted capacity may
create operational problems (such as reducing Shipper’s
ability to respond to an OFO under GT&Cs Section 15),
Shipper may be subject to a contract-specific flow
requirement on its retained segment or must be willing to
take other remedial action acceptable to Pipeline.
(d) Within 15 days after the close of the bidding period,
Pipeline will notify Shipper of the winning bid(s).
Shipper then shall have five (5) days after receiving such
notice to notify Pipeline whether it will match the winning
bid(s). If Shipper elects to exercise its Right of First
Refusal to match the winning bid(s), Shipper’s Service
Agreement shall be amended to reflect the terms of such
bid(s).
(e) If Shipper does not exercise its Right of First Refusal,
Pipeline will execute a Service Agreement with each winning
Bidder.
4.7 Subject to this Section 4, on the expiration or termination of
any Service Agreement, whether for firm or interruptible service,
Pipeline will have all necessary NGA or other legal authority to
abandon or terminate such service without any requirement to make
application to the Commission for such authority.
4.8 Regardless of anything stated in this Section 4, Pipeline shall
not be required to provide service at any rate less than the
applicable Recourse Rate.