Carolina Gas Transmission Corporation

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/2006, Docket: CP06- 71-001, Status: Effective

Original Sheet No. 117 Original Sheet No. 117 : Effective

 

2. REQUESTING AND CONTRACTING FOR SERVICE

 

2.1 Service Request. Shippers seeking new service from Pipeline or

changes to existing services, excluding changes to Primary

Receipt or Delivery Points under Section 2.4, must: (i) submit a

completed request for service in the form on, and containing the

information described on, the Internet Website; and (ii) comply

with the creditworthiness provisions under GT&Cs Section 3.

 

(a) If Shipper’s request for service does not comply with this

Section 2, or if Shipper’s creditworthiness does not comply

with GT&Cs Section 3, Pipeline shall notify Shipper of the

deficiencies and of the additional information or changes

required to complete the Service Request within five (5)

Business Days of Shipper’s submitted complete request.

Shipper shall have the right to supplement Shipper’s

Service Request as thus required for a period of ten (10)

days after such notice. If Shipper’s Service Request, as

supplemented within ten (10) days after such notice, is

satisfactory to Pipeline, then Shipper’s original Service

Request date shall be used. Pipeline shall act on such

satisfactory Shipper Service Requests in order by date of

original receipt. If Shipper’s Service Request, as

supplemented within ten (10) days, remains unsatisfactory,

incomplete, or otherwise deficient, Shipper’s entire

Service Request shall be deemed void.

 

(b) If Shipper’s Service Request and creditworthiness comply

with these GT&Cs and if Pipeline determines that capacity

is available to provide the requested service without

impairing its ability to render existing firm services,

Pipeline will tender to Shipper a Service Agreement. If

the Service Agreement is not executed and returned within

15 days, the Service Agreement shall be invalid and

Pipeline promptly shall return any security or collateral

given by Shipper under GT&Cs Section 3.

 

(c) If Pipeline determines that Shipper’s Service Request would

require the construction of facilities, Pipeline will

notify Shipper of such determination. If within 30 days of

Pipeline’s notice Shipper does not request Pipeline to

construct facilities under Section 2.2, the Service Request

shall be invalid and Pipeline promptly shall return any

security or collateral given by Shipper under GT&Cs Section

3.