7.3 In the event that batch flowing nominated volumes of less than 10,000

Dth per Day is deemed operationally impractical by Transporter or Liberty, and

should Liberty receive nominations for the injection or withdrawal of Gas,

which after aggregation with other nominations commencing at the same time and

same meter, results in a net metered volume less than or equal to 10,000 Dth

per Day, Liberty will attempt, but shall not be required, to schedule such

nominations. However, if any single nomination or combination of nominations

is scheduled such that the aggregated nominated volumes result in a net metered

volume less than or equal to 10,000 Dth per Day, all nominations may be

curtailed on a pro rata basis such that the net metered volume will be zero.

Liberty will orally notify the affected Customer(s) within four (4) hours of

being notified of changes to nominations which would result in curtailment as

provided herein.

8. NOMINATIONS AND SCHEDULING

8.1 During any Day when Customer desires Liberty to inject, withdraw or

wheel Gas, Customer shall submit a nomination to Liberty via fax or via the

Internet Web Site that includes, but is not limited to, the following

information: quantity, flow period, upstream transportation contract number(s),

downstream transportation contract number(s), Customer name and Storage Service

Agreement number, and the Customer's authorized employee name and telephone

number. All nominations shall be based on a daily quantity.

All nominations shall include Customer defined begin dates and end dates. All

nominations, excluding intraday nominations, have rollover options.

Specifically, Customers have the ability to nominate for several Days, Months,

or years, provided the nomination begin and end dates are within the term of

Customer's Storage Service Agreement.

Overrun quantities should be requested on a separate transaction.

8.2 Liberty will accept nominations for service as follows:

(a) Next Day Service. The nomination timeline on the Day prior to the Day

of Gas flow shall be the following:

11:30 a.m. Nomination leaves control of the Customer

11:45 a.m. Receipt of nomination by the Transporters (including from Title

Transfer Tracking Service Providers (”TTTSPs”))

12:00 p.m. Liberty provides quick response for validity of data

elements

3:30 p.m. Completed confirmations from upstream and downstream

connected parties provided to Liberty

4:30 p.m. Receipt of scheduled quantities by Customer and point

operator

The sending party shall adhere to nomination, confirmation, and scheduling

deadlines. It is the party receiving the request that has the right to waive

the deadline.