Liberty Gas Storage, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/15/2007, Docket: RP07-357-000, Status: Effective
Original Sheet No. 122 Original Sheet No. 122 : Effective
GENERAL TERMS AND CONDITIONS
5. PRIORITY, INTERRUPTION OF SERVICE AND OPERATIONAL FLOW ORDERS
5.1 Priority of Service. Any Customer executing a Storage Service
Agreement with Liberty shall be entitled to the storage, parking, wheeling,
loaning, imbalance trading, or balancing of Gas in the following order of
declining priority:
(a) Firm Storage Service (FSS) at primary Point(s) of Receipt, not in
excess of MDRQ, and at primary Point(s) of Delivery, not in excess of MDDQ,
located on Liberty's system.
(b) Firm Storage Service (FSS) at secondary Point(s) of Receipt or Delivery
located on Liberty's system, and Firm Storage Service (FSS) at primary Point(s)
of Receipt located on Liberty's system, in excess of MDRQ but less than or
equal to MDIQ, and Firm Storage Service (FSS) at primary Point(s) of Delivery
located on Liberty's system, in excess of MDDQ but less than or equal to MDWQ,
and all Secondary Firm Storage Service (SFS).
(c) Make-up volumes to correct prior variances between (i) Transporter and
the counterparty to a balancing agreement (pursuant to such agreement), (ii)
Customer and Liberty, and (iii) Customer and Transporter if the variance was
due to Liberty's failure to receive or deliver Customer's scheduled volumes.
(d) Interruptible service, including Excess Injection Gas and Excess
Withdrawal Gas
(pursuant to Section 2 of Rate Schedules FSS and SFS), parking, wheeling,
loaning, imbalance trading, and/or balancing service pursuant to Section 5.2
below.
(e) Extended injections for firm storage service in excess of MDRQ/24 or
extended withdrawals for firm service in excess of MDDQ/24.
(f) Extended injections for secondary firm storage service in excess of
MDRQ/24 or extended withdrawals for secondary firm service in excess of
MDDQ/24.
If a capacity constraint is anticipated or planned (for example, due to system
maintenance), Liberty shall post a notice of the anticipated constraint on its
Internet Web Site at least 48 hours in advance of the start of the constraint
period.
5.2 The order of priority relating to service requests for Excess Injection
Gas and Excess Withdrawal Gas (pursuant to Section 2 of Rate Schedules FSS and
SFS) and service under Rate Schedules IP, IW, IL, IBT and IB shall allocated to
each Customer on a pro rata basis.