Liberty Gas Storage, LLC
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/15/2007, Docket: RP07-357-000, Status: Effective
Original Sheet No. 108 Original Sheet No. 108 : Effective
GENERAL TERMS AND CONDITIONS
3.5 Additional Information.
(a) Customer or prospective Customer shall also promptly provide such
additional Customer credit information as may be reasonably required by
Liberty, at any time during the term of service under a Storage Service
Agreement, to enable Liberty to determine Customer's or prospective Customer's
creditworthiness.
(b) After receipt of a request for service, Liberty may require that
prospective Customer furnish additional information as a prerequisite to
Liberty offering to execute a Storage Service Agreement with such prospective
Customer. Such information may include proof of prospective Customer's lawful
right and/or title to cause the Gas to be delivered to Liberty for service
under this FERC Gas Tariff and of prospective Customer's contractual or
physical ability to cause such Gas to be delivered to and received from such
prospective Customer's designated Point(s) of Delivery and/or Receipt.
(c) Should a Customer or a prospective Customer desire Liberty to provide
service
pursuant to Section 311 of the Natural Gas Policy Act, it shall provide to
Liberty a statement warranting that it complies with all requirements for
receiving service pursuant to Section 311 and the FERC's regulations
thereunder, including, but not limited to, compliance with the “on-behalf-of”
requirement then in effect.
3.6 Request Validity. If Liberty has tendered a Storage Service Agreement
for execution to a prospective Customer and such prospective Customer fails to
execute the agreement as tendered within
30 consecutive days from the date it receives the agreement, Liberty may
consider prospective Customer's service request void. For service under Rate
Schedule FSS or SFS, Liberty will not be required to tender a Storage Service
Agreement to a prospective Customer for execution that relates to requests for
service for which Liberty does not have sufficient available firm or secondary
firm capacity.
3.7 Customer's Performance. Customer is required to provide to Liberty
information identifying (1) the State of the source of Gas that is to be stored
and/or transported and (2) such other information if required in order for
Liberty to comply with any FERC reporting or other requirements.
3.8 Complaints. In the event that a Customer or prospective Customer has a
complaint relative to service under this FERC Gas Tariff, the Customer or
prospective Customer shall provide a description of the complaint, including
the identification of the service request (if applicable), and communicate it
to:
LIBERTY GAS STORAGE LLC
Contract Administrator
101 Ash Street
San Diego, California 92101
Telephone: (619) 696-2266
Facsimile: (619) 699-1816
e-mail: LibertyContractAdmin@SempraPipelines.com
Liberty will respond initially within forty-eight (48) hours and in writing
within 30 days of receipt of the complaint advising Customer or a prospective
Customer of the disposition of the complaint. In the event the required date
of Liberty's response falls on a Saturday, Sunday or a holiday that affects
Liberty, Liberty shall respond by the next Business Day.