Black Marlin Pipeline Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/01/2002, Docket: RP02-454-001, Status: Effective

Substitute Second Revised Sheet No. 211A Substitute Second Revised Sheet No. 211A : Effective

Superseding: First Revised Sheet No. 211A

GENERAL TERMS AND CONDITIONS

(continued)

 

The total receipt nominations must equal the total delivery

nominations, with the exception of quantities nominated to

correct an imbalance.

 

A package ID is a way to differentiate between discrete business

transactions. When used, Package ID should be supported for

nominating, scheduling, allocating, and invoicing (sales and

purchase), and not required for transportation invoicing. Use

of the Package ID is at the discretion of the service requester,

and if sent, should be accepted and processed by the service

provider.

 

If Shipper fails to comply with provisions (1) through (4) of

this Section 9.1.A, Transporter shall not schedule the

commencement of service or change to a prior nomination.

Transporter supports a seven-days-a-week, twenty-four-hours-a-

day nominations process. It is recognized that the success of

seven-days-a-week, twenty-four-hours-a-day nominations process

is dependent on the availability of affected parties scheduling

personnel on a similar basis. Party contacts need not be at

their ordinary work sites, but should be available by beeper.

 

Overrun quantities must be scheduled as a separate transaction.

 

B. Nomination Timeline

 

Transporter and Shipper shall support the following minimum

NAESB standard nomination cycles as set forth below in (1) and

(2). Such nomination opportunities shall represent the grid-

wide synchronization times across the North American pipeline

network.

 

(1) Nominations for the Upcoming Gas Day

 

(a) The Timely Nomination Cycle. 11:30 a.m. for

nominations leaving control of the nominating party;

11:45 a.m. for receipt of nominations by Transporter

(including from Title Transfer Tracking Service

Providers (TTTSPs)); noon to send Quick Response; 3:30

p.m. for receipt of completed confirmations by

Transporter from upstream and downstream connected

parties; 4:30 p.m. for receipt of scheduled quantities

by Shipper and point operator (Central Clock Time on

the day prior to flow).