Kinder Morgan Illinois Pipeline LLC

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/01/2007, Docket: RP08- 34-001, Status: Effective

Substitute Original Sheet No. 123 Substitute Original Sheet No. 123 : Effective

 

GENERAL TERMS AND CONDITIONS

----------------------------

 

(notice to bumped parties), (central clock time on the Day prior to

flow). Scheduled quantities resulting from an Evening Nomination that

does not cause another Service Requester (Shipper) on KMIP to receive

notice that it is being bumped should be effective at 9:00 a.m. on the

Day; and when an Evening Nomination causes another Service Requester

(Shipper) on KMIP to receive notice that it is being bumped, the

scheduled quantities should be effective at 9:00 a.m. on the Day.

 

(c) The Intra-Day 1 Nomination Cycle: 10:00 a.m. for

nominations leaving control of the nominating party; 10:15 a.m. for

receipt of nominations by KMIP; 10:30 a.m. to send Quick Response; 1:00

p.m. for receipt of completed confirmations by KMIP from upstream and

downstream connected parties; 2:00 p.m. for KMIP to provide scheduled

quantities to affected Shippers and point operators, and to provide

scheduled quantities to bumped parties (notice to bumped parties),

(central clock time on the gas Day). Scheduled quantities resulting from

Intra-Day 1 Nominations should be effective at 5:00 p.m. on the Day.

 

(d) The Intra-Day 2 Nomination Cycle: 5:00 p.m. for

nominations leaving control of the nominating party; 5:15 p.m. for

receipt of nominations by KMIP; 5:30 p.m. to send Quick Response; 8:00

p.m. for receipt of completed confirmations by KMIP from upstream and

downstream connected parties; 9:00 p.m. for KMIP to provide scheduled

quantities to affected Shippers and point operators (central clock time

on the Day). Scheduled quantities resulting from Intra-Day 2 Nominations

should be effective at 9:00 p.m. on the Day. Bumping is not allowed

during the Intra-Day 2 Nomination Cycle. In addition, KMIP will allow

Intra-Day Nominations, subject to confirmation and scheduling priorities,

outside of the standard NAESB nomination cycles referenced in Section 6.2

of these General Terms and Conditions if the timing of the nomination is

consistent with an allowed nomination cycle in the "Interconnecting Point

Operator's" tariff.

 

(1) For purposes of Section 6.2(d), "Interconnecting

Point Operator" shall mean the interconnecting pipeline entity

immediately upstream of the Receipt Point as defined in Section 1.28 of

these General Terms and Conditions.

 

(e) For purposes of Section 6.2 (b), (c), and (d), "provide"

shall mean, for transmittals pursuant to standards 1.4.x, receipt at the

designated site, and for purposes of other forms of transmittal, it shall

mean send or post.

 

(f) The rights of a Releasing Shipper to recall capacity

within any nomination cycle shall be governed by Section 14.14 of these

General Terms and Conditions.