Rockies Express Pipeline LLC (Entrega)
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/12/2009, Docket: RP09-890-000, Status: Effective
First Revised Sheet No. 424 First Revised Sheet No. 424
Superseding: Original Sheet No. 424
FORM OF SERVICE AGREEMENT Contract No.__________
APPLICABLE TO POOLING AND WHEELING SERVICE UNDER
RATE SCHEDULE PAWS
(Continued)
8. RATES:
Commodity Rate:
(Pursuant to Section 5 of Rate Schedule PAWS of the Tariff)
Maximum applicable rate per Tariff as revised from time-to-time, unless otherwise agreed to in
writing as a discount or negotiated rate (pursuant to Sections 12.6 and 33, respectively, of
the General Terms and Conditions of the Tariff.)
L&U Reimbursement Percentage:
(Pursuant to Section 5.2(B) of Rate Schedule PAWS of the Tariff)
Maximum applicable rate per Tariff, as revised from time-to-time, pursuant to Section 38 of
the General Terms and Conditions, unless otherwise agreed to in writing as a negotiated rate
(pursuant to Section 33 of the General Terms and Conditions of the Tariff.)
Incremental Facility Charge:
(Pursuant to Section 5.3(B) of Rate Schedule PAWS of the Tariff)
_____None
_____Lump-sum payment of _________
_____Monthly fee of _______ through (date, period of time or event).
9. NOTICES TO TRANSPORTER UNDER THIS AGREEMENT SHALL BE ADDRESSED TO:
Rockies Express Pipeline LLC
Attn: Marketing
370 Van Gordon Street
P.O. Box 281304
Lakewood, CO 80228-8304
E-mail: WRGP@kindermorgan.com
Shipper Approval: Transporter Approval:
SHIPPER: ____________________________________ TRANSPORTER: Rockies Express Pipeline LLC
SIGNATURE: SIGNATURE:
TITLE: TITLE: