Rockies Express Pipeline LLC (Entrega)
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2007, Docket: CP06-354-002, Status: Effective
Original Sheet No. 231 Original Sheet No. 231 : Effective
GENERAL TERMS AND CONDITIONS
18. MEASUREMENT (Contd.)
18.9 NEW MEASUREMENT TECHNIQUES
If, at any time, a new method or technique is developed with
respect to Gas measurement or the determination of the factors
used in such Gas measurement, such new method or technique may be
substituted by Transporter in exercise of its reasonable judgment.
Transporter shall promptly inform all Shippers of any new
techniques adopted.
18.10 CALIBRATION AND TEST OF METERS
The accuracy of all measuring equipment shall be verified by
Transporter at reasonable intervals, and if requested, in the
presence of representatives of Shipper, but neither Shipper nor
Transporter shall be required to verify the accuracy of such
equipment more frequently than once in any thirty (30) Day period.
If either party at any time desires a special test of any
measuring equipment, it will promptly notify the other, and the
parties shall then cooperate to secure a prompt verification of
the accuracy of such equipment.
18.11 CORRECTION OF METERING ERRORS
If, upon any test, any measuring equipment is found to be
inaccurate, such equipment shall be adjusted immediately to
measure accurately. If, upon any test, the measuring equipment in
the aggregate is found to be inaccurate by one percent (1%) or
more at a recording corresponding to the average hourly rate of
Gas flow for the period since the last preceding test, any
payments based thereon shall be corrected pursuant to Section 12.5
of these General Terms and Conditions, at the rate of such
inaccuracy for any period which is known definitely or agreed
upon, but in case the period is not known definitely or agreed
upon, such correction shall be for a period extending over one-
half (1/2) of the time elapsed since the date of the last test.
Measurement data corrections should be processed within six (6)
Months of the production Month with a three (3) Month rebuttal
period. This standard shall not apply in the case of deliberate
omission or misrepresentation or mutual mistake of fact. Parties'
other statutory or contractual rights shall not otherwise be
diminished by this standard.