GENERAL TERMS AND CONDITIONS
12. STATEMENTS, BILLING, PAYMENT, RATE DISCOUNT ORDER AND TYPES OF DISCOUNTS
(Contd.)
12.5 ADJUSTMENT OF ERRORS (Contd.)
B. Prior period adjustment time limits shall be six (6) Months
from the date of the initial transportation invoice and
seven (7) Months from date of initial sales invoice with a
three (3) Month rebuttal period, excluding government-
required rate changes. This standard shall not apply in the
case of deliberate omission or misrepresentation or mutual
mistake of fact. Parties' other statutory or contractual
rights shall not otherwise be diminished by this standard.
C. In no event will any changes be made after twenty-four (24)
Months from the date of statements, billings or payment,
based on actualized volumes, unless the parties mutually
agree.
D. Any error discovered as a result of a timely claim shall be
corrected within thirty (30) Days of the determination
thereof. Parties' other statutory or contractual rights
shall not otherwise be diminished by this standard.
12.6 RATE DISCOUNT ORDER AND TYPES OF DISCOUNTS
A. Rate Discount Order
If and when Transporter discounts the rates and charges
applicable for service under any Rate Schedule, the
components of the currently applicable Maximum Rate shall be
discounted in the following order: The first item of the
overall charge discounted will be any surcharge, followed by
the base rate charge. Any surcharges will be attributed in
accordance with the applicable section of the General Terms
and Conditions that provides for the surcharge as
established in individual proceedings.