Rockies Express Pipeline LLC (Entrega)
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2007, Docket: CP06-354-002, Status: Effective
Original Sheet No. 123 Original Sheet No. 123 : Effective
GENERAL TERMS AND CONDITIONS
4. RECEIPT POINTS
4.1 FACILITIES AT RECEIPT POINTS
Unless otherwise agreed by Transporter, Transporter shall own,
operate and maintain all pipeline and measurement facilities
necessary to receive and measure Gas hereunder. In the event that
any facilities are installed by Transporter, Section 6 of these
General Terms and Conditions shall apply.
4.2 OBLIGATION
Transporter's maximum obligation to receive Gas at the Receipt
Point(s) under the Agreement shall never exceed the lesser of:
(a) the applicable MDRQ under the Agreement in the aggregate or at
individual Points, as specified in the Agreement or as applicable
to any Point under this Tariff; or (b) the total daily volume
Shipper or its designee is able and willing to tender at the
Receipt Point(s).
4.3 LOCATION
Unless otherwise described in the Agreement, the Receipt Point(s)
for transportation Agreements shall be located at the
interconnection between the facilities of Shipper, or its
designee, and the facilities of Transporter.
5. RECEIPT AND DELIVERY OF GAS FOR THE ACCOUNT OF SHIPPER
5.1 RECEIPT AND DELIVERY VOLUMES
A. Commencing on the date of first acceptance by Transporter of
Gas delivered by or on behalf of Shipper at the Receipt
Point(s) pursuant to an Agreement, and continuing thereafter
during the term of that Agreement, Transporter shall deliver
Equivalent Volumes, or cause Equivalent Volumes to be
delivered, to Shipper or to a mutually agreeable third
party for Shipper's account, at the Delivery Point(s)
described in the Agreement or applicable to the Agreement
under this Tariff pursuant to Section 5.1B and C, below.