Centerpoint Energy Gas Transmission Company
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/28/2003, Docket: RP03-239-000, Status: Effective
Original Sheet No. 878 Original Sheet No. 878 : Superseded
STATEMENT OF NEGOTIATED RATES
Contract Rate
Shipper Name Number Schedule Contract Demand Receipt Point(s) Delivery Point(s) Rate 2/ 3/ 4/ 6/
------------ -------- -------- ------------------ ---------------- ------------------------------- ------------------------
Baptist Health 1003109 FT 119 Dth/d North Pooling Area At the point of interconnection $0.15/Dth (expressed as
System -Parkway Neutral Pooling Area between CEGT's transmission unit rate at an assumed
Village facilities and the facilities of 100% load factor)
Reliant Energy Arkla, a division
of Reliant Energy Resources Corp.
near Little Rock, AR where deliveries
are made for use in Shipper's facility
1/ Standard Rate and Related Provisions for Non-Maximum Rate Agreements, shown in the CEGT News section of CEGT's Internet web site "pipelines.centerpointenergy.com",
shall be applicable to this transaction. Rates include any applicable GRI, ACA, GT&C Section 13.4, Order No. 528 and Order No. 636 transition surcharges.
2/ If Transporter unable to collect contemplated Negotiated Rates for any reason during term, Transporter may elect to convert agreement to maximum rates; Shipper will
have termination right in such event.
3/ Unless otherwise agreed, rate applicable to specified receipt/delivery points and only to authorized quantities up to Contract Demand.
4/ Shipper must pay Reservation Charge each month based on CD, no matter quantity transported, calculated as a unit rate (on an assumed 100% load factor basis) by
subtracting minimum applicable Commodity Rate from unit rate.
5/ Authorized overrun rate is greater of maximum applicable overrun rate or applicable unit rate shown hereon.
6/ $0.04/Dth add-on to the Commodity Rate for receipts from the North Pooling Area.
7/ Unless unauthorized overrun, eligible quantities for which the initial Receipt Point cannot be determined shall be deemed to have been received as follows:
(a) if no overrun scheduled, prorated based on nominations;
(b) if overrun scheduled, prorated based on overrun nominations; and
(c) if no nominations, from point or Pool which would be charged highest rate under agreement.
8/ If Shipper releases capacity, it shall pay Transporter for any Commodity Rate charges not received by Transporter from the replacement Shipper.