Centerpoint Energy Gas Transmission Company
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2010, Docket: RP10-567-000, Status: Effective
Fourth Revised Sheet No. 729B Fourth Revised Sheet No. 729B
Superseding: Third Revised Sheet No. 729B
[FIRM (RATE SCHEDULE [FT])][FIRM WHEELING (RATE SCHEDULE PHS)]
TRANSPORTATION SERVICE AGREEMENT
(continued)
[(e) Inability to Collect Negotiated Rates: If this Agreement covers a Negotiated Rate transaction,
and Transporter is unable to collect Negotiated Rates due to a change in Commission policy or
rejection of the transaction by the Commission prior to or during the term of such transaction,
then, unless the parties agree otherwise, Shipper shall pay the maximum Tariff rate for the
services. In such event, Transporter shall notify Shipper in writing of the requirement to pay
maximum Tariff rates and, if the maximum Tariff rates are greater than the Negotiated Rates
under such transaction, Shipper shall have no more than thirty (30) days from the date of such
notification to give notice in writing of termination of the applicable Agreement, with such
termination to be effective no earlier than the end of the Month following the Month in which
such termination notice is received.]]
[5) OTHER PROVISIONS:
5.1) Payments shall be received by Transporter within the time prescribed by Section 14 of the GT&C
of Transporter's Tariff. Amounts past due hereunder shall bear interest as provided in Section
14 of the GT&C of the Tariff. Shipper shall pay all costs associated with the collection of
such past due amounts including, but not limited to, attorneys' fees and court costs. Shipper
hereby represents and warrants that the party executing this Agreement on its behalf is duly
authorized and possesses all necessary corporate or other authority required to legally bind
Shipper.
5.2) Do the parties agree that the provisions of Section 13.4 of the GT&C of Transporter's Tariff
shall apply with respect to third-party transportation?
Yes: ____ No ____
[If Yes, the terms and conditions of such third-party transportation are described [as
follows:] [on Attachment A]]
5.3) a) Does this Agreement supersede and cancel a pre-existing Transportation Service Agreement(s)
between the parties?
Yes: ____ No ____
[If Yes, the Transportation Service Agreement(s) are described [as follows: ] [on
Attachment A]]
b) Does this Agreement amend and restate in its entirety a pre-existing Transportation Service
Agreement(s) between the parties?
Yes: ____ No ____
[If Yes, the Transportation Service Agreement(s) are described [as follows: ] [on
Attachment A]]
5.4) Is this Agreement entered into pursuant to and subject to CAPACITY RELEASE, Section 19 of the
GT&C of Transporter's Tariff?
Yes: ____ No ____
[If Yes, the rights of Shipper hereunder are predicated upon the release of capacity at the
rates and terms and conditions described in the award of such capacity][.][, as subsequently
amended herein.]
5.5) Does this Agreement include any other terms/provisions permitted by the Tariff?
Yes: ____ No ____
[If Yes, those provisions (including a specific reference to the Tariff authority for each such
provision) are [as follows:] [described on Attachment A]]
[For firm wheeling (Rate Schedule PHS) agreements, Shipper [has][does not have] the right to
use an Aggregation Point in lieu of its Primary Receipt Point(s) as a Receipt Point under this
Agreement.]
[INSTRUCTIONS: If capacity committed under Agreement was created by construction of new or
expanded facilities and special collateral or credit provisions, which were negotiated prior to
construction in a precedent or other agreement, are to continue during term, insert the
following:
5.6) This Agreement is subject to the collateral or credit provisions
set forth on Attachment [A] [B], attached hereto.]