Centerpoint Energy Gas Transmission Company
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/01/2010, Docket: RP10-206-000, Status: Effective
Original Sheet No. 560B Original Sheet No. 560B
GENERAL TERMS AND CONDITIONS
(continued)
19. CAPACITY RELEASE (continued)
(c) The replacement Shipper has failed to comply with the MFO(s)
under the releasing Shipper's FT-2 Service Agreement.
20. OPERATIONAL CONTROLS:
20.1 General. All Shippers hereby agree and acknowledge that
Transporter's ability to deliver anticipated quantities and
maximize efficiency and capacity utilization is dependent upon
maintaining projected flow patterns (e.g., receipts, deliveries,
balances, storage injections and withdrawals) within optimal
ranges. Transporter shall endeavor at all times to maintain
adequate pressure through all segments of its system, maximize
operational efficiencies for the benefit of all Shippers,
preserve the operational integrity of all segments of its system,
prevent the use of the system by a Shipper in a manner
inconsistent with the Tariff which could infringe on or threaten
the rights of other Shippers, and protect