Centerpoint Energy Gas Transmission Company
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/28/2003, Docket: RP03-239-000, Status: Effective
Original Sheet No. 505 Original Sheet No. 505 : Effective
GENERAL TERMS AND CONDITIONS
(continued)
jurisdictional transportation and sales tariffs for
the same period of the customer directly served by
Transporter which is attributable to the indirect
customer by (B) for the same period, the sum of (1)
all volumes delivered off of Transporter's system
pursuant to Transporter's generally available
jurisdictional transportation and sales tariffs, and
(2) all non-jurisdictional sales made by Transporter.
(c) Relevant Absorption Level -- The sum of (i) the total
amount of CSC absorbed by Transporter pursuant to the
25% absorption obligation provided at Section 18.8(b)
up to and including the time of the filing of the
Subject Eligible CSC being challenged (which amount
shall include the additional amount absorbed as a
result of such filing); (ii) the extent, if any, to
which the relevant Subject Eligible CSC being
challenged are absorbed by Transporter as a result of
the cap provided at Section 18.8(c)(4); and (iii) the
extent, if any, to which the relevant Subject
Eligible CSC being challenged later are absorbed by
Transporter as a result of the three cents (3¢) per
Dth caps provided at Sections 18.3.1(b), 18.3.2(b),
and 18.7.1. In making the determination of the extent
to which the relevant Subject Eligible CSC have been
absorbed by Transporter pursuant to the provisions of
(ii) and (iii), all Subject Eligible CSC shall be
ranked according to date of their initial filing
pursuant to the provisions of Section 18.6.1, with
those filed earlier in time considered to be the first
to be recovered pursuant to the CSC Charge and those
filed later in time considered to be the first to be
excluded from recovery (and, therefore, absorbed) as a
result of the relevant caps. If any portion of the
amount absorbed can not be determined as of the date
of the Commission's final order on such challenge
because of the inability